Conference to remove difficulties and speed up the implementation of infrastructure investment and development projects in Tien Du district
09:45 29/08/2022
With the synchronous solutions to support the restoration of production and business in the province, in the first 6 months of the year, the index of industrial production (IIP) increased by 19.75% compared to the same period last year. This is the highest increase in the last 5 years (2018-2022) and is a prominent bright spot in the economic picture of Bac Ninh province in the first 6 months of 2022.

Following the direction of the Chairman of the Provincial People's Committee in Notices No. 75/TB-UBND and No. 77/TB-UBND dated July 19, 2021, on announcing the conclusion of the Chairman of the Bac Ninh Provincial People's Committee at the Business Dialogue Conference of the year 2021; Document No. 1252/UBND-KTTH dated May 9, 2022 on assigning the Bac Ninh Industrial Zones Authority to respond to enterprises' recommendations at the Business Dialogue Conference in 2022.

Conference Picture.

On August 24, 2022, the Bac Ninh Industrial Zones Authority in collaboration with Office of the Provincial People's Committee, the Department of Natural Resources and Environment, the Department of Construction, the Department of Transport and the People's Committee of Tien Du District, held a Conference on removing difficulties and obstacles, accelerating the implementation of IP technical infrastructure investment and development projects in Tien Du district.

Attending and chairing the conference were Mr. Nguyen Van Phuc - Director of Bacninh IZA, and the Standing Comrades of Tien Du District Party Committee: Mr. Nguyen Dai Dong - Chairman of the District People's Committee; Mr. Nguyen Cong Ky - Standing Vice Chairman of the District People's Committee; Mrs. Nguyen Thi Hao - Vice Chairman of the District People's Committee and leaders of the Office of the Provincial People's Committee, the provincial departments and branches; Leaders and specialized departments under the District People's Committee and the Bacninh IZA; Leaders of industrial park infrastructure development investment companies in the district (King Bac Investment Development Corporation – JSC, VSIP Bac Ninh Co., Ltd., Viglacera Infrastructure Investment and Development Company and Branches of JSC Saigon Telecommunications Technology in Bac Ninh) and leaders of communes whose land is in the planning of industrial parks.

At the Conference, leaders of industrial park infrastructure development investment companies (Hanaka Group Joint Stock Company, Bac Ninh Industrial Park Infrastructure Investment and Construction One Member Co., Ltd.) report on the situation and progress of investment and construction of industrial park infrastructure projects over the past time; clearly state the difficulties and problems. Delegates at the Conference have listened those reports and discussed solutions to speed up the compensation and site clearance for these projects. Thereby conducting investment in building technical infrastructure of industrial parks, attracting investors and promoting the development of the district in the coming time.

According to reports, the main difficulties affecting the implementation progress of industrial park projects are the progress of compensation and site clearance, the escalating price of materials, especially of construction materials, the transportation cost burdened by rising fuel costs in recent years.

The Bacninh IZA received comments from Tien Du District and provincial departments and branches.

After listening to the investors of industrial parks reporting on the situation and progress of investment and construction of industrial park infrastructure; difficulties and problems along with the exchange and discussion ideas of the members attending the Conference; Director of the Bacninh IZA has suggested that departments, specialized branches and consulting units coordinate with Tien Du district to focus on speeding up the resolution and removal of shortcomings and problems, creating favorable conditions for investors to accelerate project implementation; calling on secondary investors to carry out investment projects to speed up the filling up of the industrial park. At the same time, it is suggested that industrial park investors need to be more determined, take measures to build synchronous and modern industrial parks to meet the needs of investors and meet the requirements of industrial park development./.

 

Writer: Chu Duc Dao


Translated by Nguyen Mai Huong Office of Bac Ninh IZA